Linthal spinning mill - Replacement of pressure line

Kelag Holding
Kelag Holding
Left
Right

Scope of services / technical features

Our services included complete technical processing, design, static calculations, drafting of the workshop plans, material acquisition, manufacture, corrosion protection, transport and assembly including fill test and acceptance of the pressure line.

Key specifications

Length of the pressure lineLtot544m
Constant diameterDa457mm
Wall thicknesss6.3 and 8.0mm
Material qualityST 37.0 and St 52.0 with 3.1 Attest
Static pressure heightH stat.431.5 mWs
Dynamic pressure surgeH dyn.86.3 mWS of this corresponded to 20% of H stat.
Max. calculation pressurepi51.8 bar (central)

Brief description

Complete renovation of the compressed water line with constant pressure measurement DN450 and flange connections. The flange pipes were manufactured at the factory and transported to the construction site using a lorry.  The assembly work includes the assembly of the old as well as assembly of the new line in the tunnel. Transport to the construction site was carried out by railroad transport cars which we designed and built ourselves.