Fitting joint pipes
Fitting joint pipes for ADAMS blow-out preventers, delivery, assembly and corrosion protection as well as valve connection pipes
Fitting renovation Luchsingen power plant
During the fitting renovation for both turbines at the Luchsingen power plant of the Glarus workshop we were able to structurally design, deliver and mount the new expansion pipe at the DN300 PN64 headquarters.
Insertion tube central Schlappin
During the pressure line replacement, the insertion tube had to be adjusted to the new conditions and re-designed. For this purpose, a extension tube with the "pressure compensation stop plugs" was implemented.
Neubau Ferndampfleitung
Im April wurden in der Montagen AG die ersten Druckleitungs-Rohre für das Projekt „Erneuerung Kraftwerk Kaiserstuhl“ (Kunde: EW Obwalden) erfolgreich fertiggestellt.
KW Plus, additional turbine Grimsel1 armoured plate
Installation of a new pressure pipeline (armoured plate) for the additional turbine which was installed into the central Grimsel 1.
Insertion tube central Schlappin
During the pressure line replacement, the insertion tube had to be adjusted to the new conditions and re-designed. For this purpose, a extension tube with the "pressure compensation stop plugs" was implemented.
Neubau Ferndampfleitung
Sanierung des Wehr Nr. 4 Flusswasserkraftwerk Birsfelden. Die Stahl- und Maschinenbaulichen Instandsetzungsarbeiten wurden vor Ort und im Werk der MAG durchgeführt.
Linthal spinning mill - Replacement of pressure line
Complete renovation of the compressed water line with constant pressure measurement DN450 and flange connections. The flange pipes were manufactured at the factory and transported to the construction site using a lorry.
Tunnelling logistics Sedrun
Rotation incline joints for the Gotthard Basic Tunnel (Alptransit) - Manufacture of 3 rotation incline joints. The rotation incline joints are used for the creation of the Gotthard Basic Tunnel (world's largest railroad tunnel [57km] ) at the shaft in Sedrun.
VfA wet continuous-flow conveyor
The rust which accumulates under the combustion grating is collected using a sieve and is passed on through wet shafts to the wet continuous flow conveyor. The shafts are submerged into the water bath of the wet continuous flow conveyor in order to achieve a hermetic seal in relation to the primary air system / combustion chamber.
VfA slide de-sludger
Both de-sludgers are located directly below the sludge shafts. The incinerate trash sludge falls through the sludge shaft into the water bath, is extinguished and is hydraulically removed using a baffle plate.